Adding members to the Agile Team makes you go slower
As a Stakeholder or Product Owner I want I want to understand if constantly adding Agile Team members is a good idea So that I can have a valid conversation with my Product Owner and Scrum Master
Initially at least!
Velocity
When building a new AgileBI delivery team, it takes a while to achieve what is referred to as a full velocity.
Velocity is a metric used to measure the work done. At the end of each delivery iteration, the AgileBI Team adds up effort estimates associated with user stories that were completed during that iteration. This total is called velocity.
Velocity is used in the planning process to help the AgileBI Team workout what they can commit to delivering in the next 3-week iteration. They size each user story in the iteration using Poker Points and then “fill” the sprint with the user stories until the total number of points matches the velocity of the previous iteration.
It will take a new AgileBI Team 3 – 6 iterations to reach full velocity. By full velocity, I mean the average number of points the team can sustainability and successfully, deliver in 3-weeks of effort. AgileBI Teams will typically start out with a low velocity until they discover the most efficient way to work together and meet their full potential – aka full velocity.
It is important to note that the velocity of different AgileBI teams is always different and you should never compare across different teams.
Once the AgileBI Team has discovered its full velocity, the AgileBI team can also compute (or revise) an estimate of how long the project will take to complete, based on the estimates associated with remaining Information Product backlog and assuming that velocity over the remaining iterations will remain approximately the same. This is generally an accurate prediction.
Adding a new team member makes you slower
This often causes an issue when there is a fixed or desired deadline and the estimated date of completion is after the desired date of completion. The Stakeholders often find this unacceptable.
If you have a well-formed AgileBI Team that is at their true maximum velocity then the only choices you have is to either accept the estimated date of completion, reduce what you are asking them to deliver or stand up an additional AgileBI Delivery Team.
Of course, standing up an additional team of 5 to 7 AgileBI Members is often a large cost, especially when it takes 9 to 18 weeks (3 to 6 iterations) for them to achieve their full velocity.
So there is a big risk that somebody will come up with the idea of adding 1 or more new members to the current team. If the team does not have good T-Skills, or you are pipelining, you will often see the suggestion that you double some of the legacy roles. For example, adding another BA and Tester to make it “go faster”.
The issue is that adding new members to the AgileBI Team will make the whole team go slower and deliver less, at least in the short term. This is because:
- The existing AgileBI Teams members will need to train new members up in the way the team works, and this reduces what they can deliver themselves.
- New members often mean new opinions and so the way the team works may get relitigated or time is taken to explain why it was agreed to do it that way.
- The team will take time to assimilate the new skills mix and make it the team effective.
- Often there are not enough tasks for two members with similar skills, so one member will be idle for a portion of the iteration.
The danger of old delivery behaviour
I would typically say that adding team members (often referred to as “resources”) was a Waterfall behaviour. But I’m not sure that the formal Waterfall approaches such as Prince 2 actually say that when you are not on track the answer is to randomly add more resources to solve the problem.
It is definitely the behaviour of people who have no experience in Agile. Their theory being that if the Agile Team are not delivering fast enough, then the answer is that everybody must be busy and to add more people to the team. This is often done without any understanding of the root cause for the lack of velocity.
I have actually seen examples where people have been arbitrarily added to an AgileBI Team, without the team actually being told the new members were turning up. Also without the project manager who was adding the people actually attending the retrospectives to ensure it was not a problem with the AgileBI process.
In fact in one example when the Project Manager and Scrum Master announced they were adding another “BA” I asked the experienced Agile Team members if they actually needed more members, they said no it was the last thing they needed.
What they said they needed was clarity of what was to be delivered each sprint and for the Scrum Master, Business Analyst and Project Manager to stop randomly removing deliverables from the Sprint, when the deliverable seemed “hard”.
To be clear these deliverables were “descoped” during the sprint, not at the sprint backlog session before the sprint commenced. They were removed by the Project Manager and the Scrum Master, not by the AgileBI Team. They were also removed not because the Agile Team said they had miss-estimated and couldn’t deliver them during the sprint, but just because they looked hard to certain members when the real effort was discovered.
At that time the Agile Team were many sprints down and had formed and stormed as a team. But the desired delivery velocity was not there and there was a fixed deadline to decommission a legacy system. It was very clear that at the current velocity the data and content would not be replaced in time for the fixed deadline.
A number of issues were obvious with the Agile Approach that was being used.
For whatever reason, the Scrum Master had yet to introduce story pointing for the Sprint. In addition, a pipeline approach was implemented which meant there was a BA and a SME “documenting” requirements in the first sprint, the data skilled members developing the data in the second and the content and testing skilled members doing their tasks in the third sprint.
The AgileBI Members that highlighted any issues that needed to be worked on in subsequent sprints during the retrospectives, were flagged to the “leadership team” that they were causing issues. The fact that there was even a “leadership team” when there was only one single AgileBI Delivery Team, was a warning in itself.
The BA and the SME were reverse engineering the requirements from code and content that had been delivered over decades, rather than engaging with the key users to understand what they needed today.
A “business advisor” outside of the AgileBI Team (i.e not the Product Owner) was making the call on what data and content needed to be delivered to enable the old system to be decommissioned. Another “advisor” from the BI software company who had never worked in an Agile environment before, and was remote to the AgileBI Team, and was providing part-time “expertise” on the Agile Approach that should be used.
At the start of the time-period the AgileBI Team had to replace the data and content, the organisation had undertaken a massive reorganisation that changed every employee’s role. This caused massive disruption when trying to get access to the key users or when the Product Owner needed to engage with Stakeholders to help get key decisions made.
There were a large number of Agile Process problems to solve before even thinking about adding new members to increase velocity.
AgileBI Discipline Articles
Qlik Sense Desktop – Loading QVD
When using the Qlik Sense Desktop you can easily add Excel or CSV files to your new application by selecting them in the add data window. What I missed was the fact that this option also allows you to add a QVD easily as the source file. Just select "All Files" and...
Trifacta – Wrangling Dates (and yet another open data rant)
One of the pieces of data we use regularly is dates. Every data repository needs the ability to view the data by day, month, year, etc. There is often also a need to view data based on holidays. Funnily enough, you would think that a list of data containing the NZ...
Guided vs Discovery vs Blending Information Products
I have seen a massive change in the business intelligence, data and analytics tools our customers are buying and using over the last couple of years. The advent of data wrangling tools such as Trifacta, open-source analytics tools such as R and visual exploration...
AgileBI Delivery
As a BI Practitioner
I want to understand how to deliver in an AgileBI way
So that I can deliver faster and with less risk
AgileBI Team
As a BI Practitioner I want to understand what an AgileBI team is and isn't So that I know how to form and storm one Building a self organising team is one of the key factors required to deliver in an AgileBI way. Creating a team with T-Skills and helping...
AgileBI Discipline
As a BI Practitioner
I want to understand what AgileBI Disciplines are
So that I know what Disciplines to follow (and what Disciplines not to)
Evaluating BI tools – Don’t get left hanging
Evaluating BI tools used to be easy. You either took a stack approach and picked a vendor first, then selected the modules you wanted to use from their product catalog. Or you picked one thing you wanted to do extremely well and selected a best of breed product/vendor...
Hans Hultgren – The 2016 NZ Data Vault Certification Tour
As you may have worked out if you have been reading our blogs for a while, we are big fans of the Data Vault approach as a way of automating the Integration layer of a Data Warehouse (DW). In 2014, we sent a couple of our DW experts to Sydney to attend Hans...
The challenges and risks of being an Agile BI Manager
As a BI manager who decides to empower their team by introducing an AgileBI approach, there is a massive amount of risk in that simple action.